Projects / ESL-2

ESL-2 recovery system, from design to prototype

2025 to 2026Estaca Space Launcher program, Estaca Space Odyssey student societyStructures and mechanical design / Assembly, integration and test / Project management
Prototype built, bench ejection test done
Annular volume
25 mm thick
Diameters
200 outer 150 inner, mm
Main parachute
10 m²
Locking
6 axial pins
Team
5 people, 9 months
Budget
EUR 400

I was the recovery team project manager. I did all the CAD, managed the budget, handled integration and represented the project at society meetings. The team built and assembled the prototype together.

Assembly animation in Fusion 360
Constraint
A 25 mm thick annular volume that must still clear a 10 m² parachute
Design
Catapult ring on linear rails, nose cone held by 6 pins released by actuators
Build
Machined steel tube, PETG and nylon parts, assembled and integrated
Result
Bench ejection test passed
Next
Containment bag being made, qualification and integration tests in 2026-2027
01

Context and constraints

Starting point

ESL-1 flew on July 11, 2025, reaching about 2,800 m apogee. With the team, I analyzed the flight from onboard video and axial accelerometer data in Excel. The main parachute deployed early, which we traced to the nose cone opening shock. Planète Sciences had also flagged excessive nose cone rocking, caused by a shoulder that was too short and by large clearances.

We took over the recovery system as a PITA, the supervised year-long team project of the third year at ESTACA.

Constraint

The lengthened shoulder made a full redesign of the nose cone ejection necessary. The mechanism had to fit into a 25 mm thick annular volume, 200 mm outer diameter and 150 mm inner diameter, and still clear a 10 m² parachute.

The ESL-1 flight we analyzed. Downward camera up to apogee, then upward camera for the ejection.

02

Design

Principle

A spring-loaded catapult ring guided on linear rails pushes the nose cone out. Until then, the nose cone is locked by 6 axial pins released by electric linear actuators. The main parachute is packed in a fabric bag closed by petals held by a cord, opened on command by a servo that winds the cord onto a drum. Detailed CAD in Fusion 360.

Sizing

Spring stiffness sized in MATLAB from a force balance, chosen for a clean ejection without excessive exit velocity. The catapult ring is loaded in compression against the locked nose cone.

Failure modes first

Before freezing the design, I looked for the configurations that could make it fail. The linear rails guide the ring to limit the risk of binding. The lock stays closed without power. The actuators are powered only for release, which reduces the risk of an unintended opening after a board reset under liftoff vibration.

1. Locked
2. Pins released
3. Nose cone pushed out
4. Separated

Interface ring

The interface ring was one of the key parts of the project. On ESL-1 it had been 3D printed in plastic, and we were asked to make it machinable.

Fusion 360 drawing of the interface ring, 206 mm diameter
Interface ring drawing in Fusion 360, sheet 1 of 2

Machining simulation of the interface ring in Fusion 360

03

Build

Machined steel tube and PETG and nylon printed parts, then assembly and integration. The three large threaded rods belong to the bench frame only. The rings are at the 200 mm nominal diameter, ready to receive the carbon composite skin.

Upper section
Central section
Lower section
Linear rail and carriage, springs, electric linear actuators and 3D printed mounts
04

Tests

First assembly

Most subassemblies worked the first time.

Issues found and fixed

Some clearances were too tight and were fixed by reprinting or sanding. One actuator mount was under-constrained. Its push finger drifted off axis and bore on the frame, leaving the nose cone locked. The mount was corrected, and the current prototype completed a bench ejection test. We counted it as passed once the nose cone came fully out several times in a row.

Locked
CAD
Prototype
Ejection
CAD
Prototype

Same mechanism, as designed in Fusion 360 and as built. Prototype frames from the ejection test video of May 9, 2026.

05

Current status

The parachute containment bag is being made. The parachutes will be made once the final mass of the rocket is known. Full ground ejection, structural and integration tests remain planned for 2026-2027.